Behind the frame

SCROLL

Back

Elia

22 September 2025

Turning a complex construction site into memorable images.

On paper, it’s “just” a pylon head replacement.

On site, it’s an industrial choreography where every second counts.

For Elia, we covered the replacement of three pylon heads — a key operation within a programme of 62 interventions on the 220 kV Lixhe–Jupille line.

Objective

Extend the lifespan of the infrastructure

and strengthen the reliability of the network.

The constraint?

Some areas were inaccessible to cranes.

The solution: the helicopter.

Thanks to meticulous preparation and flawless coordination, the teams turned a constraint into an operational success.

Our role

Tell this performance through images:

  • controlled angles,
  • the timing of manoeuvres,
  • safety at the heart of every operation,
  • precision in technical gestures.

Result

A clear, readable visual narrative,

serving technique, communication

and the long-term memory of the project.

Share

At Melting Prod, we like it when the technical challenge is demanding.

Because these are the projects that deserve to be told with accuracy.

Respect to all teams involved.

A complex industrial project to document?

We know how to make technology speak.

hello@meltingprod.eu

Click here to discover our “industrial” portfolio